Part 1 received
The Part 1 application is the applicant’s notice to the NRCB that they will be submitting an application to expand an existing CFO or construct a new one. When the Part 1 application is received, the approval officer establishes the minimum distance separation (MDS) and provides the municipality with a copy of the application.
Part 1 application
Part 2 received
The applicant must submit their completed Part 2 application within six months of submitting the Part 1. They may ask for an extension of up to six months to submit their Part 2. If the application is not submitted within six months, and the applicant did not request and was not granted an extension, the applicant must re-submit their Part 1 application. The MDS is reset as of the date the NRCB receives the new Part 1.
Deemed complete
The application is deemed complete when all technical requirements are met. If the applicant needs to provide more information before the application can be deemed complete, they may request an extension of up to six months. When the application is deemed complete, the approval officer begins to process the application, and to track the number of working days to decision release. The approval officer:
- sends a copy of the deemed complete application to the municipality and other referral agencies, as relevant to the application.
- issues notice and sends notification letters to parties within the directly affected party notification distance for approval and registration-sized applications (if the municipality is able to provide their contact information). The parties are given 20 working days to respond to the application by submitting a response. (Notice is not required for authorizations.)
- may meet with the applicant to discuss the responses. The applicant may need to provide more information to respond to the issues raised. Some applicants choose to revise their application in response to these issues.
- reviews the technical details of the application to ensure it meets the requirements of AOPA. The approval officer also conducts environmental risk screenings of the existing and proposed facilities to determine if they could pose a risk to groundwater and surface water, and confirms the application’s consistency with the land use provisions in the municipality’s municipal development plan. The approval officer then determines what conditions may apply.
Decision documents
The approval officer finalizes the technical review document and writes the decision summary and permit.
- The decision summary explains how the application meets or doesn’t meet the requirements of the act; examines and responds to issues raised by referral agencies or in responses received; explains how the application does or doesn’t comply with the land use provisions in the municipal development plan; addresses technical issues and explains what conditions will be attached to the permit, if any, and why.
- The permit states the permitted facilities and livestock species and numbers, the conditions that are attached to the permit, the construction deadline, and the requirement for a post construction inspection. The permit also consolidates any previously-issued permits.
- The technical review document provides the detailed record of the environmental risk assessments and other technical aspects of the review.
Decision issued
The approval officer contacts the applicant to review the permit and any conditions attached to the permit, including the need for a post-construction inspection and timeline for the inspection.
Copies of the decision, permit and technical document are provided to the applicant and the municipality. All of the decision documents are posted on the NRCB website.
The deadline to submit a request for review to the Board of the NRCB to appeal the decision is set out in the approval officer's decision cover letter. The number of working days to issue a decision are calculated and recorded.